2019-2020
METINVEST ENGINEERING
Reconstruction of 1700 Sheet Rolling Shop at Steel Mill named after Illych
2018-2020
METINVEST ENGINEERING
Sinter machines reconstruction at Steel Mill named after Illych
2018-2019
METINVEST ENGINEERING
Capital maintenance of blast furnace # 3 at Azovstal Steel Mill
2018-2019
METINVEST ENGINEERING
Continuous Casting Machine Plant # 4 construction at Steel Mill named after Illych
2017 - 2018
METINVEST ENGINEERING, LLC
Dismantling, civil & erection, commissioning works of a Fume Treatment Plant under the project Converter Shop Fume Treatment System Reconstruction at PJSC "AZOVSTAL IRON & STEEL WORKS".
2017
PJSC Ukrgrafit - Reconstruction Project of the existing plant with continuous graphite furnace
- Equipment erection;
- Piping work;
- Electrical erection works;
- Accompanying of commissioning.
SMS Group (Germany)
Fabrication of non-standard equipment for ArcelorMittal Krivoy Rog
2015-2016
- repair and refurbishment of PCI equipment;
- fabrication of special structural elements for proper disassembly of equipment under revision;
- nticorrosion protection of steel structures and oversize equipment.
Erection of four-beam overhead crane for ArcelorMittal Krivoy Rog
2014-2015
New ring furnace erection project
- civil works;
- mechanical erection;
- piping erection;
- electrical installation.
2012
- Mechanical erection;
- Piping erection;
- Electrical installation works;
- Regular maintenance.
2011-2012