JSC “PE “Techmash” performed contract work on the reconstruction project “INSTALLATION OF BENZENE SCRUBBER AND FINAL GAS COOLER” at PJSC “ArcelorMittal Kryvyi Rih” from February to August 2016.
The project work included:
– Fabrication of metal structures;
– Installation of equipment;
– Installation of pipelines;
– Electrical installation work;
– Support of commissioning and adjustment works.
The project was implemented under the conditions of existing production.
The contractor demonstrated flexibility, efficiency in making technical and organizational decisions, as well as the appropriate level of quality in performing installation works within the agreed schedule.
All internal procedures of PJSC “ArcelorMittal Kryvyi Rih” on safety, labor protection and fire safety were complied with by JSC “PE “Techmash”.